Last update - Sep 20 2002 by Darien Davis

LM status

Current status at LM -- Testing ER localization at SITSF
Eastern Range software installed and being tested

Task Status thru October 2003

Latest 5.1.2 patch is "r"; now testing with 5.2.2 at FSL

ER localization complete
Tabular point data being tested
Enhancement -- export to D2D to briefing tool Waiting for test plans
Enhancement -- multi-color range ring background Complete
Range Ring upgrades Testing

Build 5.2.2a (October 2002)

Enhancement -- RedHat 7.2 Staged at FSL
Enhancement -- AWIPS 5.2.2 Creating regression test plan
Level II radar ingest Staged and testing
Level III radar ingest Staged and testing
Informix and text workstation Staged and testing
MDPI/WINDX Waiting for user feedback
Enhancement -- split LDAD data sets into different directories Staging
Enhancement -- Tabular text thresholding Waiting for test plans
Tall Tower ingest and display Part of split LDAD data sets

Build 5.2.2b (March 2003)

LDAR prototype Design review, 9/23 with ENSCO, LMCO
LPLWS (field mill) Design review, 9/24 with LMCO,ENSCO
contouring wind divergence Waiting on response from Clay Flinn
LLP (CGLSS) Requirements review, 9/20.02
74C Contacted ER POC
User Towers Not started
Prototype for Remote system Not started
Text RAOB Not started

Build 5.2.2c (October 2003)

complete LDAR
Final Remote system
Neuman-Pfeffer Index replacement
Radio Theodolite
TAF ingest and decode


Lockheed Martin Phone numbers

DCS List

ER Site and Asset List

Ldad Interface Document v8, 16 Aug 02

September Calendar

Tkgnats tracking for software

Deliverable Schedule

Current PR list

Data Ingest description

Overall RSA requirements

February

27 Jan 28 29 30
Herb on-site help
31
Herb on-site help
1
Herb on-site help
Status Meeting (1/25/02)
2
Darien on-site help
3
Darien on-site help
4 5 6 7 8 9
10 11 12 13 14
Status Meeting
15
Info on two-heads sent to LM (Wakefield)
16
17 18
Joe on-site help
19
Joe on-site help
20
Joe on-site help
21
Joe on-site help
22
Joe on-site help
23
24 25
Darien on-site help
26
Darien on-site help
27
Darien on-site help
28

March

1 2
3 4 5 6 7
Deliver rsa_512k
8 9
10 11 12 13 14 15 16
17 18
Start of testing dry run

Delivered rsa_512l

19
Joe Wakefield on site help
20
Joe Wakefield on site help
21
Joe Wakefield on site help
22
Joe Wakefield on site help
23
24 25
Continued testing dry run
26
Darien on-site help
27
Darien on-site help
28
Darien on-site help
29
Darien on-site help
30
31

April

1 2 3
Darien on-site help
4
Darien on-site help
5
Darien on-site help
6
7 8 9 10 11
rsa-512m delivery (via email)
12 13
14 15
Susan on-site help
16
Susan on-site help
17
Susan on-site help
18
Susan on-site help
19
Susan on-site help
20
21 22
Joe on-site help
23
Joe on-site help
24
Joe on-site help
25
Joe on-site help
26
Joe on-site help
rsa_512n delivery
27
28 29 30
7.2 RH upgrade on ws1-avs
RSA 5.1.2 merged into RSA 5.2.2

May

1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21
Ensco/LM onsite design discussion
22
rsa_512o delivery
23 24
end of ENSCO/LM onsite design discussions
25
26 27 28 29 30 31
Delivery of user guide, smm docs

June

1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20
AWIPS 5.2.2 RSA 5.2.2 merge
21 22
23 24 25 26 27 28 29
30

July
 
1 2 3 4 5 6
7 8 9
onsite TIM
10
onsite TIM
11
onsite TIM
12 13
14 15 16 17 18 19 20
21 22
bdds/orpg running mdorpg
23 24
Upgraded DS to RH 7.2
25 26
Installed RSA5.2.2 with ER localize
27
28 29 30 31
Storing ORPG data on mdorpg

August
 
1 2 3
4 5 6 7 8 9 10
11 12
Status meeting
13
New designs posted
14 15 16 17
18 19 20 21 22
LDAR ingest reqs review
23 24
25 26 27 28 29
RSA 5.1.2R delivered
30 31

September

1 2 3 4 5 6 7
8 9 10 11 12
LPLWS reqs review
LDAR design review
13
5.2.2 staged
14
15 16
Status meeting
17 18 19 20
LLP (CGLSS) reqs review
21
22 23
CDR ENSCO
24
CDR ENSCO
5.2.2 Charlotte
25
CDR ENSCO
5.2.2 Charlotte
26
5.2.2 Charlotte
27
5.2.2 Charlotte
28
29 30

Phone numbers:
Tim Wilfong Project Manager 805-348-2386 wk 805-878-5131 cell
Charlotte Johnson AWIPS testing 805-348-2136
Lowell Schaffert System Engineer 805-348-2227
David Flynt System Install 805-348-2360
Andy McDonald System Install 805-348-2112
Dana Andersen Network 805-614-3520
ROC 805-606-3358
SITSF 805-614-3555